Week 18 – Wrapping up the rough-in
Week 18 saw the completion of HVAC, electrical, and plumbing rough-in. Also, the dining room bar framing was completed…
First coat of Cabot white solid stain applied to the glulam beams
South elevation with a couple of beams painted. 18″ glulam over garage still needs to be ripped to 14″
48″ high “bar” framing for dining room
Another view of bar. Eight cubbies will be installed on the West side and cabinets on the East
Won’t have this view through Liam’s bedroom for long. Sheetrock install coming soon!
Foamboard insulation
Mop sink rough-in complete
Gas dryer rough-in complete
Washer rough-in complete
In a full tadalafil from india stomach, the effectiveness is greatly reduced. The specific nature of this medicament helps to improve the body resistance to disease. respitecaresa.org viagra 25 mg Hence, if you cannot enjoy your love life because of erectile dysfunction. free generic viagra Diabetes produces symptoms like increased thirst, increased hunger, frequent urination, skin infections, delayed healing of wounds, fatigue, tadalafil from cipla weight loss/gain, irritability and erectile dysfunction.
Shower rough-in complete
Master bath rough-in with wall mounted sinks complete
Wall mount sink rough-in detail. Spout is at 41″ high. I hope that works!
Pot filler rough-in complete
Water supply for PLUMBED Miele built-in coffee maker. No more constantly filling the water container every time you want to make a cup of coffee!
Glulam with one coat of solid stain
Stained glulam
Another view of stained beams
Foam insulation has already started! Should have some good pics up on Sunday. Sheetrock install starts in nine days!