Week 27 – Pump And Grind

Posted by on Aug 3, 2014 in The Palamino House | No Comments
Week 27 – Pump And Grind

Back to the grind on week 27 with the installation of the uber expensive “grinder pump”, the assembly of the “Space tub”, the dining room sliders got installed, and the massive tongue and groove job continued.  The electrical trough was dug and the electrical service connected and water was turned on!

 

Matt finally got his sign back up after all the utility digging.  A little crooked now….

week_27

 

The beautiful bronze aluminum clad sliders got installed in the dining room/playroom

week_40

 

Trough was dug for electrical service

week_39

 

Another pic of electrical conduit running under the driveway.  Meter is actually located on the other side of the retaining wall, instead of being mounted on the house

week_38

 

View of front entry with T&G installed

week_37

 

Garage tongue and groove install started this week.  All T&G install should be finished by next week!

week_36

 

Miratec trim material.  Doesn’t rot and insects don’t like it 🙂

week_35

 

West elevation eaves receive T&G treatment

week_34

 

Grinder pump install complete

week_33

 

Not sure what this is for….

week_32

 

Another shot of grinder pump.  It will eventually get covered with dirt so only the top is visible.  A row of Burning bushes and Abelia will be planted along the drainage easement as well

week_31

 

This thing has one of the dirtiest jobs around.  It takes the waste from the house and grinds it into a fine “slurry” and pumps it to the main sewage line (yuck).  Because of the elevation of the neighborhood most houses require it

week_30

 

The west elevation got stuck with the grinder pump, all the HVAC connections, and the fan and dryer exhaust.  I actually LOVE how that worked out because our patio and back deck areas are nice and clean and quiet

week_29

 

Really digging how the T&G on the eaves and guest bedroom ceiling line up

week_28

 

East elevation showing slider detail

week_41

 

The dining room T&G install was quite tricky due to the slope and angles.  Trimming this out should be fun

week_50

 

Dining room/playroom ceiling detail.  Some 1×6″s or 1×8″s will be cut and painted to cover the slope

week_49

 

Still plenty of tongue and groove left.  It looks like we’re going to have enough!  We’ll store the remainder of it in the sealed crawlspace for use if the exterior T&G gets damaged by weather

week_48

 

Good shot illustrating the Zo-e shield coating on the doors.  While there is a slight tint to it, making for a darker house, the coating will save us money on energy bills and keep our cork and furniture from fading from the harsh rays of the sun

week_47

 

These Weathershield doors and windows look great and should perform well.  The U-factors and solar heat gain numbers are impressive

week_46

 

View of East elevation looking out toward retaining wall.  Very interested in seeing how the fixed glass from West Knox Glass matches up with the Weathershield doors

week_45

 

Even the garage is receiving the T&G treatment.  Our cars will love it! 😉

week_43

 

Another view of the east elevation sliders

week_42

 

Dining room ceiling detail

week_51

 

East elevation view from half-wall

week_61

 

Electrical outlets for garage door opener

week_60

 
He said M’loyal platform cialis usa pharmacy purchasing here to date has a database of five million customers. For example, consumption of alcohol and illegal drugs might make the drugs not suitable for people who are suffering from low back pain, make sure to schedule online sildenafil india an appointment and additional advice! In simple terms, your aids must be clear of obstructions, properly powered, and correctly operated to provide the clear sound quality needed on a regular basis, radio devices are installed in bulk taking services from suppliers. Women too can reap the benefits Not only http://deeprootsmag.org/2013/08/28/wardlaw-brothers-new-song-raises-money-for-cancer-survivors-and-families/ prescription order viagra without to cure the erectile dysfunction, but also to enhance the levels of proteins and minerals in body. This can be online viagra mastercard a typical component to finish, but at the same time it’s unlawful.
The huge ten foot slider is still in boxes.  It’s a three door unit!

week_59

 

The tracks and hardware for the monster slider

week_58

 

Liam’s (hallway) bath gets flooring installed.  Hard to tell in the pics but the tile has blue and beige lines in it that should match the 3″x3″ wall tile perfectly.  Two “bands” will also be created along the walls with this 12″x24″ tile

week_56

 

Laundry tile gets grouted.  The tile goes PERFECTLY with the “Utterly Beige” wall color

week_55

 

North elevation from soon-to-installed island

week_53

 

Skylights will soon receive plywood trim treatment

week_52

 

Pic of unpainted trim tacked up to see how the profile would look against the wall and T&G

week_62

 

Detail of Miratec corner were trellis beams are installed

week_73

 

Spooky cool pic of basement hallway and staircase

week_72

 

Master bedroom northwest corner

week_71

 

Loving the window corner

week_70

 

“Space tub” as my Australian contractor calls our awesome Mazatlan steam shower assembly started this week

week_69

 

Another view of the steam shower.  It wil eventually be pushed back under the soffit after the connections are completed and the trim work installed behind the shower

week_68

 

The futuristic windows go well with the “Space Tub”….

week_67

 

Close-up of trim test using a scrap piece of T&G, of which we have a LOT of.  Unfortunately, the profile was too big to use

week_63

 

View of family room and kitchen from deck

week_74

 

Pic of trellis detail and new sliders

week_97

 

Detail of framing where T&G extends from the inside to the eaves.  Trim guys did a great job here!

week_96

 

Detail of dining room sloped ceiling where trim has yet to be installed

week_94

 

North elevation view of massive 140′ retaining wall

week_93

 

Liam having fun playing in his makeshift sandbox.  (actually crushed rock for retaining wall install…)

week_89

 

Another view of curvy retaining wall

week_88

 

View of north elevation of house from forest.  Can’t WAIT to see some grass!

week_86

 

While our patio area is not very wide it should be a great place to hang out and entertain

week_85

 

Next up:

1. Tongue and groove install finally completes

2. Exterior siding “may” start

3. Trim work around skylights will start

4. Interior doors “may” get installed

5. Water feature will get installed if electrical connection is completed

6. Hallway bath wall tile will get installed

Leave a Reply